Eastgate Renewable Energy Village |
|
| Name of the project | Eastgate Renewable Energy Village |
| Country | United Kingdom |
| Description | Using solar, wind, hydro and biomass sources to generate electricity, the community surrounding the area can reap the benefits of increased employment and tourism as well as low cost and sustainable energy. The project is now in the finalizing stages of gaining permission to start the development. At this stage the ownership of the area will transfer to the community, free of charge. |
| Project developer | Weardale Task Force |
| Start date | 30-11-1999 |
| Financing sources | Grant from the dept of energy and climate change. |
| Initiator | Weardale Task Force |
| Investor(s) | Lafarge Cement, One NorthEast, local community |
| Project owner | Weardale Task Force |
| Actors who receive benefits | Local community, non profit organisation still to be created |
| Legal background | The project is mainly possible because the cement company wished to return the area to the community, free of charge, in a way which would be beneficial to its economic development. Currently, the municipality is in the process of researching any liabilities concerning this transaction prior to accepting it. |
| Background information | With the departure of the local cement company (Blue Circle was bought by Lafarge Cement UK ) from the cement quarry, Eastgate lost a large source of income and employment. It was therefore promised by Lafarge Cement UK. that there would be an alternative use for the location, one that would restore economic benefits in the community. When a geothermal source was found, providing naturally heated water of a quality usable for a spa, the area was immensely attractive to use as a eco-friendly touristic destination. |
| Type of benefit sharing mechanism | Benefits in kind Local contracting Local employment Indirect social benefits |
| Renewable energy source | Wind power Hydropower Solar energy Bio-fuel Geo-thermal energy |
| Application of BSM | Benefits in kind: Local contracting: The work which needs to be done in the development stages of the project is delegated to local contractors as much as possible, generating temporary employment for the local community. Local employment: As the project will result in a small scale renewable energy showroom, there will be permanent employment in maintenance and operation. Furthermore, there will be indirect effects due to the increased tourism, which will generate jobs in hospitality businesses, as well as other economic activities. Indirect social benefits: The project is designed to attract various sectors of tourism, as it provides for a spa as well as a showroom for five different methods for harvesting renewable energy sources. |
| Roles of the different stakeholders | The Lafarge Cement company facilitates the project by donating the area to the community. Local government stimulates the project by streamlining the process of permit application, having a facilitating role between the developers and the local community, as well as providing information to its citizens. |
| Impact of BSM of this project on socio-political level or market acceptance | This project is one of the first in the UK which uses such a large variety of energy sources. If the project works out to be as successful as anticipated, the use of renewable energy sources as a (new) source of income to a region as well as an attraction for tourists, could be stimulated and repeated within the country as well as in the rest of Europe. |
| Website | http://www.davidlock.com/weardale2/ |
Koepel Windenergie Noordoostpolder |
|
| Name of the project | Koepel Windenergie Noordoostpolder |
| Country | Netherlands |
| Description | The project consists of 3 land-based parks with a total capacity of 200 MW and 2 near-shore parks with a capacity of 200 MW. When completed it will be largest wind project in the country. By using 3 to 5 MW turbine models the number of individual turbines is planned to be around 80-100. All five parts of the project are maintained and monitored by Windkoepel Noordoostpolder, an organization which consists of all the various investors (including private citizens), landowners and municipal governments. |
| Project developer | KoepelNOP |
| Start date | 01-01-2000 |
| Financing sources | Shareholder Equity Subsidies (SDE and Investment Subsidy) Debt Financing |
| Initiator | Various local organizations, mainly farmers and land owners |
| Investor(s) | Government subsidies of 880 million to be paid over 15 years, 116 million to be paid in two tranches, ,furthermore there will be debt financing of approximately 400 million through banks and 100 million private equity of which 75% is available for participation. |
| Project owner | Windkoepel Noordoostpolder |
| Actors who receive benefits | Shareholders |
| Legal background | Local farmers were placing wind mills on their property in the beginning of the 90's, which urged the local government to introduce new legislation which regulated the placement of these wind turbines, as the scattered layout would pollute the scenery of the area. |
| Background information | The initiative for starting this project comes from local land owners and farmers, who incorporated themselves into small cooperatives to build windmills on their own land. The municipality rejected these initiatives and placed them in broader perspective by starting the process of developing a big wind farm; yet still involving the farmers. The 3 projects on land are owned by these landowners and the benefits will therefore be divided by them. Participation in the project by the communities Noordoostpolder, Lemsterland and Urk is only available for the part which stands offshore. |
| Type of benefit sharing mechanism | Community fund Local ownership/co-ownership |
| Renewable energy source | Wind power |
| Application of BSM | Community fund: The municipalities of Nagele, Tollebeek, Espel, Creil and Rutten will recieve an annual amount of 10.000 euro for a period of 20 years. This money can be used for local projects and activities. Local ownership: All the citizens of the Noordoost Polder and the municipalities of Urk and Lemsterland can participate in two out of five parts which make up this project. The participation schemes have not been defined yet, but should be made available in various sizes and amounts of risk exposure, so that everyone can participate. The aim is to have a maximum of 20% of the project owned by local citizens. Co-ownership: The initiative for the park came when various land owners and famers in the region wanted to install new wind turbines on their land or replace existing ones. In return for combining these initiatives in a larger park, the individual parties are combined in cooperatives, owning three of the five parts in this project. |
| Factors which contributed to the success of the project | Governmental support was crucial in the subsidy process, as this allowed for an adaptation in the subsidy regulations regarding the SDE, which led to a higher amount (total of 880 million instead of 693 million) of subsidy to be granted to the project. Furthermore, an additional subsidy in the amount of 116 million was granted to the project for its innovative nature. The government also played a role in the fute between the Windkoepel and neighbour community Urk. To make a concession against the opposition in this municipality, the government decided to remove the 7 turbines located closest to them from the original plans and include them in the participation scheme. |
| Roles of the different stakeholders | Farmers and Landowners: initiated the process of replacing old turbines or installing new ones on their land. After the idea was launched to combine these initiatives in one structured wind park, they accepted a participative role and combined their efforts in cooperatives, responsible for the development of part of the project. Municipality: ensured the various individual intitiatives were grouped allowing for a larger scale project, and plays a facilitative role between the project, the community and the national government. National Government: this park will be the largest in Europe, with a substantial contribution to the CO2 reduction targets the government aims for. The national government facilitates the project by providing subsidies, structuring the legislative aspects of the park and all permits involved as well as extensive communication with opposing parties. |
| Difficulties which had to be overcome | Due to combining various individual initiatives in one, large project, there was much more legislation to take into account then would have been the case if each wind turbine was viewed individually. For example, research on the effects of such a large park on the local environment, e.g. the bird population. An issue has been the opposition from the citizens of the municipality of Urk, located closely to the project, but without any legislative authority as the project is not on its grounds. This municipality feels that the project will harm its historical appearance severely and therefore objects to its existence. Introducing a participation mechanism to the Urk population has not been effective in reducing this opposition to a more acceptable level.The government has therefore decided to remove 7 wind turbines which were closely located to their border from the plans. |
| Impact of BSM of this project on community acceptance | Community fund: The five municipalities to whom the community funds are paid out are the ones with the most effect of the wind park on their view. Local ownership: Owning a part of the project, or the possibility to, develops a broader base for acceptance as the community reaps part of the benefits of the wind park and therefore experiences less annoyance from the negative effects, such as sound and sight effects. Co-ownership: The land owners get to keep their stake in the project, just as if they would have developed it themselves. Their involvement allows the project to be developed, as they provide the land. If they would not have been able to do this, they would have been a difficult source of resistance, as they own the land on which part of the park is built. |
| Impact of BSM of this project on socio-political level or market acceptance | There is impact on the socio-political level, as this project encouraged cooperation between the national and local government, the various municipalities and the local community members involved as a method to realise local initiatives. |
| Planned production of MW by your project | 430 MW |
| Website | www.windkoepelnop.nl |
El Hierro 100 % RES Island |
|
| Name of the project | El Hierro 100 % RES Island |
| Country | Spain |
| Description | The project at El Hierro aims at creating a 100% sustainable energy sources island. Using wind turbines, a hydro powerplant as well as PV installations and solar thermal collectors, with possible extentions towards biomass, the inhabitants of El Hierro should be independent of fossil fuels in the near future. |
| Project developer | Gorona Del Viento El Herrio S.A. |
| Start date | 30-11-2004 |
| Total investment (€) | 60 Million |
| Financing sources | Private equity Subsidies |
| Initiator | The Government of the Island El Herrio |
| Investor(s) | Public ( EU and Regional) and Private, managed by a consortium ‘Gorona del Viento S.A.’ whose shareholders are: the Island Government, the Canary Island through the participation of the Instituto Tecnico de Canarias (ITC), the utility company UNELCO- ENDE |
| Project owner | Gorona Del Viento El Herrio S.A. |
| Actors who receive benefits | Stakeholders and the local community |
| Legal background | The European Commission (DG TREN) granted financial support to a consortium of 7 partners, coordinated by ITC (Instituto Tecnológico de Canarias), to carry out the project ‘Implementation of 100% RES Project for EL Hierrio Island – first phase’ which objectives were the design and construction of the Hydro-Plant, the installation of the 500m2 of solar thermal collectors, the installation of 50kwp of grid connected photovoltaic systems and the assessment of potential for the exploitation of biomass. |
| Background information | With 276 km² and more than 10.890 inhabitants, El Hierro electricity demand was mainly covered by a conventional thermal power station (13MW diesel-fired system). The focus on renewable energies (RES) started in 1997 with the approval of the “Sustainable Development Plan” which defined a strategy to become a 100% RES island. After a first phase of studies and planning, the construction of the Wind-Hydro Plant has started, which should be able to cover nearly 80% of the Island’s electricity demand. The system is linked to a water desalination plant to fill reservoirs and produce water for irrigation and domestic use. Seminars and campaigns have been run to increase citizens' acceptance of the project and it was decided to directly involve the citizens as co-owners of the wind-hydro plant. The El Herrio was recognized by UNESCO in 2000 'World Wide Reserve of Biosphere” as space which represented an insular development model and laboratory. |
| Type of benefit sharing mechanism | Local ownership/co-ownership |
| Renewable energy source | Wind power Hydropower |
| Application of BSM | Local ownership/co-ownership: Part of the shares of the Island Government in the Gorona del Viento, the consortium created to manage the wind-hydro plant, will be divided into smaller shares in order to offer the opportunity of co-ownership to El Hierro Small-Medium Enterprises (SMEs) and every islander. |
| Factors which contributed to the success of the project | The Island’s characteristics as a ‘stand-alone’ island, facilitate the implementation of a self sufficient energy system and increase the citizens' involvement in political decisions. The willingess to cooperate amongst the wide range of actors involved ( El Herrio Government, Canary Islands Government, Utilities and Research Centers, citizens). European Union and regional funding supports and promotes the project to set an example for others islands, giving El Hierro the opportunity to become a ‘showcase’ for islands and attract eco-tourism. Organizing awareness-raising campaigns, including the publication of brochures, leaflets and information in relevant journals as well as the organisation of workshops, seminars and prestations in conferences. |
| Roles of the different stakeholders | The Consortium 'Gorona del Vento' owns and exploits the power station is formed by: - Island Government El Herrio, representing the political commitment and is the essential link for the citizens participation the project; -The Instituto Tecnico de Canarias (ITC) researches innovative solutions; -The utility company UNELCO- ENDESA provides expertise in the technical contruction and management of the plant |
| Difficulties which had to be overcome | Socio- economic problems were caused by the huge initial investment for a small economy, with little information available in the market as it was one of the first of its kind and the project was of a highly innovative nature. Furthermore, some technical difficulties had to be overcome, as the power network was not strong enough. |
| Impact of BSM of this project on community acceptance | Local ownership/co-ownership: Public acceptance of the shift towards renewable energy was increased by the possibility of being directly involved as co-owners of the Wind-Hydro Power Station and the possibility to have drinkable water produced in the island. |
| Impact of BSM of this project on socio-political level or market acceptance | Due to its scale and wide variety of renewable energy sources, the project has an impact on market acceptance of RES projects due to its exemplary properties. |
| Planned production of MW by your project | Wind Farm 11, 5 MW, Hydroelectric Substation 11,3 MW, Pumping Station 6MW |
| Website | http://www.insula-elhierro.com/ |
Samsø renewable energy island |
|
| Name of the project | Samsø renewable energy island |
| Country | Denmark |
| Description | In 1997 the Danish Ministry of Energy arranged a competition among Danish islands to become 100% self-sufficient in energy based on renewables. The proposal from the Samsø island was assessed to be the most feasible and realistic. The concept builds on energy saving measures and the following and the construction of eleven 1 MW land based mills, ten 2,3 MW off shore wind turbines and four small straw-fired district heating plants. |
| Project developer | Samsø Energy company |
| Start date | 01-01-1997 |
| Total investment (€) | Approximately 48 million |
| Financing sources | Shareholder equity Debt-finance Subsidies from the government |
| Initiator | Samsø municipality and Samsø Environment and energy office as response to the competition arranged by the Ministry of Energy |
| Investor(s) | Land turbines: The total investment was € 9 million. € 7.36 million financed by the farmers owing the land (9 turbines). € 1.64 million financed by a cooperative with 430 shareholders (two turbines) |
| Project owner | Citizens of the island, the municipality and private investors |
| Actors who receive benefits | Citizens of the island, the municipality and private investors. |
| Legal background | The Danish law on electricity supply had at that time a provision ensuring a minimum price for electricity produced by wind turbines in the first 10. Thus, the minimum sales price for the first 12,000 KWh was € 0,08 and thereafter it was € 0,06. |
| Background information | The citizens were involved from the start in the planning of the project and all aspects have been debated continuously. The plans and projects have been adjusted along the road due to input from the local community and at the end the entire community accepted and supported the plans. |
| Type of benefit sharing mechanism | Local ownership/co-ownership Local contracting Local employment |
| Renewable energy source | Wind power Bio-fuel |
| Application of BSM | Co-ownership: Local co-ownership was offered to the citizens of the island in relation to both the land and the offshore wind turbines through cooperatives. Local contracting: In the period from 1998 to 2007 it is estimated that 20 fulltime jobs were created in relation to planning and construction of the projects. Especially when it came to the construction of the land based wind turbines and the district heating plants, local labour was used. However, these jobs do not exist any more, as the projects have been completed. Local employment: Now 6 people are occupied at Samsø Energy Academy advising the island citizens about energy projects and energy saving and sharing the experience gained through the renewable energy island project to the outside world. |
| Factors which contributed to the success of the project | Local community involvement. The outset of the project was an overall master plan which was approved by the ministry of energy. This has been an important tool throughout the project implementation. Political and financial support and involvement from the municipality. Fixed minimum price for the for electricity produced by wind turbines . |
| Roles of the different stakeholders | It was the municipality that submitted the application for the competition to be renewable energy island. In order to organize the project and involve the citizens, a secretariat was established by a local NGO "Samsø energy and environment office". Later on, the energy company "Samsø Energy company" was established in order develop the specific projects and ensure the financing. This company was established by the municipality, the local trade organization and Samsø energy and environment office. When the majority of the projects were established the energy company was closed down. A new organization has been established under the name Samsø Energy Academy. Its role is to further develop the project , give professional advice to citizens considering to develop their own projects as well as to disseminate the experience . |
| Difficulties which had to be overcome | According to the master plan bio gas plants should have been part of the overall project. The island produces sufficient manure and organic waste. However, as the price for electricity generated from bio gas was too low, it turned out not to be feasible. |
| Impact of BSM of this project on community acceptance | The possibility for the citizens to become shareholders has created a positive attitude towards renewable energy installations in the community. The focus on renewable energy has encouraged many people on the island to engage in small private projects such as private solar panels and heat pumps. |
| Impact of BSM of this project on socio-political level or market acceptance | There is great interest from other parts of Denmark as well as internationally to learn from Samsø´s experience. It has created a great deal of "renewable energy tourism". These are frequently visitors from the Far East. |
| Website | http://www.energiakademiet.dk/ |
Le Haut-des-Ailes |
|
| Name of the project | Le Haut-des-Ailes |
| Country | France |
| Description | The project consists of 22 wind turbines erected in the Lorraine region. Each turbine has a capacity of 2MW amounting to a total capacity of 44MW. The farm is one of the largest in France and impacts 50 communities, directly or indirectly. |
| Project developer | Erelia (GDF Suez) |
| Start date | 01-09-2005 |
| Total investment (€) | 50 million |
| Financing sources | Shareholder equity Debt financing Subsidies |
| Initiator | Erelia |
| Investor(s) | Local Community, FIDEME |
| Project owner | Local Community, Erélia |
| Actors who receive benefits | Local Community |
| Legal background | In France the 'Taxe Professionnelle' is a tax based on the 'rental value' of corporate real estate which accrues solely to the local municipality. This tax has played an important role in making renewable energy projects attractive to rural communities seeking to revitalise the local economy. As rural municipalities are often avoided by enterprises, they lack tax funds to reinvest in community projects. Rural communities, however, often have good locations for wind projects, which induced the interest of developers. The additional funds rural municipalities raised through the 'Taxe Professionnelle' and reinvested in the community has helped increase local political support and community acceptance in France. In 2010 it was announced that the 'Taxe Professionnelle' would be replaced by a tax on the land value of the enterprise. It remains to be seen if this will have an impact on the local political support for new developments |
| Background information | The regional council from the Lorraine Region, wished to realise a renewable energy project which stimulated sustainable local development and involved the local community. In erecting the wind farm the developer held several consultation phases with the local community ensuring they were fully informed about the new development. The consultation phases included public meetings, setting up stakeholders groups which could be consulted and executing polls. Furthermore, a charter consisting of 12 principles, covering aspects such as noise limits or other nuisances, were agreed upon between the community and the developer guaranteeing a sustainable development. The developer also offered the community the possibility of buying shares in the project, a first in France. |
| Type of benefit sharing mechanism | Community fund Local ownership/co-ownership Compensation Local contracting Local employment Indirect social benefits |
| Renewable energy source | Wind power |
| Application of BSM | Community Fund: the several communities surround the wind farm earn funds from the development in the form of the 'taxe professionnelle' (approx €6000 per turbine per year) which can be spent in the respective communities. Local Ownership: Le Haut-des-Ailes was the first wind farm in France offering shares to the local community. Shares were offered at the price of € 1000. Shareholder's can expect a return of approximately 7% annually. Compensation: land owners who host the turbines are compensated in the form of annual land-use payments. A protocol was signed between the developer and the land owners to ensure an equitable distribution of these payments. Local contracting: part of the investment price was reserved for local companies (mostly engineering and construction companies) during the construction of the farm. Local employment: 4 on-site full time employees were hired for maintenance of the wind farm. Indirect social benefits: the community actively tries to promote eco tourism. The wind farm is part of the 'Renewable Energy Route' and an initiative of the organisation "Lorraine Energies Renouvelables". |
| Factors which contributed to the success of the project | Political support was an essential success factor. The local region wished to stimulate the development of wind farms in the region with a high level of consultation and involvement of the local community. The developer was very open in its communications with the community, agreeing on several principles before construction began. Thanks to the open communication, clear agreements and benefits offered the community played a decisive role in creating acceptance. |
| Roles of the different stakeholders | Local Authorities: initiated the concept of a wind farm project with a high level of community involvement and engage themselves to help develop ecological tourism which provides indirect benefits to the community. Developer: Communicate clearly & invite the community to participate Municipalities & Region: Initiated the idea of the project where the community would be involved and engaged itself to develop ecological tourism which provides indirect benefits to the community. |
| Impact of BSM of this project on community acceptance | The host of benefits offered to the community clearly had an impact on the community acceptance of the project. Only 18 months were required between the study phase of the project and acquiring the construction permit, which demonstrates the high level of acceptance for this project. |
| Impact of BSM of this project on socio-political level or market acceptance | Le Haut-des-Ailes was the first wind farm in France to offer the local community a share in the project. As a pioneering project it provided an example for other comparable projects. |
| Planned production of MW by your project | 44 MW |
| Website | http://www.ereliagroupe.fr/accueil/nos-parcs-eoliens/le-haut-des-ailes/ |
Bouin |
|
| Name of the project | Bouin |
| Country | France |
| Description | The Bouin wind farm consists of 8 wind turbines with two different owners. Three turbines of 2,5MW are owned by the Régie d'Electricité de Vendée, while 5 turbines with a capacity of 2,4MW are owned by SIIF, a subsidiary of EDF Energies Nouvelles. The wind farm completed construction in 2003. |
| Project developer | SIIF / Régie d'Electricité de Vendée |
| Start date | 01-01-2003 |
| Total investment (€) | 23 million |
| Financing sources | Shareholder equity |
| Initiator | SIIF / Régie d'Electricité de Vendée |
| Investor(s) | SIIF / Régie d'Electricité de Vendée |
| Project owner | SIIF / Régie d'Electricité de Vendée |
| Actors who receive benefits | Shareholders, Municipality, Community |
| Legal background | In France the 'Taxe Professionnelle' is a tax based on the 'rental value' of corporate real estate which accrues solely to the local municipality. This tax has played an important role in making renewable energy projects attractive to rural communities seeking to revitalise the local economy. As rural municipalities are often avoided by enterprises, they lack tax funds to reinvest in community projects. Rural communities however often have good locations for wind projects, which raised the interest of developers. The additional funds rural municipalities raised through the 'Taxe Professionnelle' and reinvested in the community has helped raise local political support and community acceptance in France. In 2010 it was announced that the 'Taxe Professionnelle' would be replaced by a tax on the land value of the enterprise. It remains to be seen if this will have an impact on the local political support for new developments |
| Background information | The French department of the Vendée wished to promote renewable energy within the territory. The site in the community of Bouin was identified as ideal due to low population density, good wind conditions, proximity to grid connection and absence of protected zones. After several consultation rounds with the local community the municipality accepted the project to its potential benefits for the local community and the possibilities of new income for the community. When completed in 2003 it was the largest wind farm in France. |
| Type of benefit sharing mechanism | Community fund Compensation Local employment Indirect social benefits |
| Renewable energy source | Wind power |
| Application of BSM | Community Fund: considering the municipality's rural character the additional taxes in the form of the 'Taxe Professionnelle' represents a significant increase in its budget. The additional taxes gained represent approximately 10% of the municipality's annual budget allowing several new public projects to be undertaken. Compensation: the farm is located near a lake where several unique birds nest. LPO, a bird protection agency, required compensatory measures to be taken before agreeing with the development. These included a ban on hunting certain birds, underground electricity cables and the execution of certain public works on the lake to improve the birds' habitat. An annual study, performed by the LPO and funded by the developers, demonstrates no higher rates of mortality amongst birds since the completion of the wind farm. Indirect social benefits: the wind farm has had a clear impact on the number of tourists visiting the municipality. Each summer approximately 18.000 cars pass the municipality daily on their way to the south of France but hardly any tourists stopped. Since construction on average 1000-1500 tourists stop daily to visit the wind farm generating income for the local community. The wind farm also served as a prestige project for the community. Besides being the largest wind farm in France at the time, it served as an educational example for other French communities considering their own farm. |
| Factors which contributed to the success of the project | Political willingness to refocus the economy and create benefits for the community. |
| Roles of the different stakeholders | The local authorities, and in particular the mayor, have played an essential role in supporting this project and realising benefits for the community. All the benefits to the community are mostly based on the initiative of the local authorities to promote eco tourism and invest the additional tax revenue on community projects. |
| Difficulties which had to be overcome | A lawsuit was filed in the planning fase of the project by bird-protection group (LPO), which supported the development but demanded certain compensatory measures be taken. The developer agreed upon the measures which included a ban on hunting certain birds, underground electricity cables and the execution of certain public works on the lake to improve the birds' habitat. A second lawsuit was filed by "l'Association pour la Sauvegarde et la Valorisation des Pays du Gois", a landscape conservation group. They denounced the 'gigantic and disproportionate' size of the project and its impact on the landscape, and disputed the construction permit. They have however withdrawn their suit in 2005. |
| Impact of BSM of this project on community acceptance | The direct link between the construction of the wind farm and the increase in tourists and revenues has created a large acceptance within the community for the wind farm. In a survey in 2003, 94% of the local community approved of the wind farm and 87% of the members of the surrounding community. |
| Impact of BSM of this project on socio-political level or market acceptance | The project was one of the first large wind farms in France and provided a large amount of funds in the form of local taxes to the municipality. These additional incomes for the municipalities provided a strong incentive for other rural communities to analyse the potential for wind farms in their region. |
| Planned production of MW by your project | 19,5 |
| Website | http://www.bouin.fr/page.php?id=12 |
Småkraft |
|
| Name of the project | Småkraft |
| Country | Norway |
| Description | Småkraft ltd. is a power company formed by 5 other Norwegian power companies with the aim to develop small scale hydro power plants in a feasible and environmental freindly way. This is done through collaboration with the local land owners. |
| Project developer | Småkraft Ltd. |
| Start date | 30-11-1999 |
| Total investment (€) | Not known |
| Financing sources | Shareholder equity |
| Initiator | Småkraft Ltd. |
| Investor(s) | Småkraft Ltd. and the land owners |
| Project owner | Småkraft Ltd. and the land owners |
| Actors who receive benefits | Småkraft and local land owners |
| Type of benefit sharing mechanism | Local ownership/co-ownership |
| Renewable energy source | Hydropower |
| Application of BSM | Each project is a collaboration between Småkraft Ltd and the landowner(s), based on a contract running for 40 years. Småkraft contributes with capital and know how. The land owners contribute with the water resources. The profit is shared between the two parties. The sizes of each party's shares are unknown. Currently there are 200 projects in 84 different municipalities, involving a total of 700 landowners. |
| Roles of the different stakeholders | Småkraft providing the capital and expertise Landowners providing the water resources |
| Impact of BSM of this project on community acceptance | The project does not influence the community acceptance as such. Sharing the profit between the landowners and Småkraft is a precondition for developing the projects. |
| Planned production of MW by your project | 2300 GWh |
| Website | http://www.smaakraft.no/ |
Texel Energy |
|
| Name of the project | Texel Energy |
| Country | Netherlands |
| Description | Texel Energy is a small scale energy company which supplies energy originating from renewable energy sources to consumers on the island of Texel, as well as to those in the rest of the country. The company started out with supplying the energy it purchased from other producers, but has the goal to be self-sufficient in the future, using geothermal, hydro, wind, biomass and solar power. The first step towards this was taken when the first windmill was put in service in the beginning of 2010. |
| Project developer | Texel Energy |
| Start date | 01-01-2007 |
| Financing sources | Shareholder equity Subsidies |
| Initiator | A group of Texel citizens, starting up Texel Energy |
| Project owner | Shareholders |
| Actors who receive benefits | Shareholders, Texel community |
| Legal background | Texel Energy does not aim at making a profit. It uses the proceeds to invest in the company, which will be beneficial to the local Texel economy. Investments are made in the use of new technology for renewable energy harvesting, such as tidal waves for electricity. The island can be used as an example for other area's, a sort of showroom of various renewable energy projects. The Texel economy will also be stimulated through the creation of jobs within the projects itself. |
| Background information | Texel energy appeals to the Texel inhabitants due to its small scale. The company has an office on the island, which can be visited freely, customers do not feel the distance they experience with large companies and call centres. With a population of only 13.783 the small scale approach is sustainable. Texel Energy has been successful in their bottom-up strategy as they started out as a small company, located on the island with close ties to their consumers, a method which appealed to their target market and therefore created a substantial consumer base. With a steady income the investments for self generation of renewable energy could be made. |
| Type of benefit sharing mechanism | Local ownership/co-ownership Local contracting Local employment Energy price reduction Indirect social benefits |
| Renewable energy source | Wind power Hydropower Solar energy Bio-fuel Geo-thermal energy |
| Application of BSM | Local ownership/co-ownership: Customers of Texel Energy buy shares by becoming a member, at a fee of €50. This membership allows them to use the energy supplied by Texel Energy at a discounted rate. Memberships can also be purchased by anyone who wishes, without the obligation of becoming a customer. Local contracting: Texel Energy aims to use local employees for the construction of its expanding business model as much as possible. Local employment: The goal is to use sustainable energy sources on the island to produce all the electricity and heat required. The harvesting of these sustainable resources will create new employment opportunities. Furthermore, as that most of the shareholders are Texel citizens,each investment made into the company benefits the local economy. Energy price reduction: When becoming a member, the renewable energy is supplied with a discount. Indirect social benefits: These stem from the potential Texel has in becoming a showroom due to the innovative technologies Texel Energy plans to put to use in the near future. Even though the island is already a popular destination for tourists, the renewable energy projects will increase this due to its appeal to a broader crowd, and will spread the flow of tourism more evenly towards the colder months. |
| Factors which contributed to the success of the project | Texel Energy is successful because it used a bottom-up technique, which means that it started small and is proceeding in achieving its goals by taking incremental steps. The first step was to attract investors through co-ownership. Most of these investors are also consumers, making sure there is a steady source of income. The next step is to not only deliver renewable energy, which is purchased from another supplier, but to also produce locally. Wind energy is now produced by Texel Energy and the goals is to take gradual steps towards an island fully reliant on renewable energy sources. With the bottom-up approach, Texel Energy did not need to look for large investors or apply for large sums of government funding. Slowly but steadily the company can achieve its goals. By staying small it remains true to its initial values, to be a local energy supplier, supplying to the Texel community. |
| Roles of the different stakeholders | Local consumers enable Texel Energy to develop, as they provide the initial capital through their membership fee and an income base through their consumption. The local and national government have supplied Texel Energy with subsidies, which are put in place for initiatives which increase the share of renewable energy sources in the total energy supply, as well as initiatives which promote the use of these renewables. Texel Energy applies both these characteristics, and therefore qualified for these subsidies. |
| Impact of BSM of this project on community acceptance | Community Acceptance: Texel Energy has used the small scale of the Texel community and the value that it places on local initiatives, local companies to develop a strong relationship with its consumers. The fact that the company is founded by locals with an aim to cater to locals creates strong support. Having a wide scale of renewable energy sources at its disposal, the implementation of the renewable energy projects as it is planned at this point will create a source of knowledge, the local community gains access to this as well. |
| Impact of BSM of this project on socio-political level or market acceptance | Texel Energy aims to have Texel become a showroom to the world. The method it takes has effect, the first windmill is in use. Texel Energy can therefore be a good example to replicate in other locations, perhaps with similar small communities. |
| Website | www.texelenergie.nl |
Hydro Projects - Local ownership improvement programs |
|
| Name of the project | Hydro Projects - Local ownership improvement programs |
| Country | Portugal |
| Description | EDP -Energias de Portugal- is developing a new approach directed to increase the community acceptance of large Hydro Projects. The methodology aims to initiate an open dialogue during the entire project in order to understand the local expectations of the project, adjust the companys' projects and to strengthen the actions from the EDP Foundation. |
| Project developer | EDP |
| Start date | 01-08-2008 |
| Total investment (€) | N/A; |
| Financing sources | Promoter of construction / EDP |
| Initiator | EDP |
| Investor(s) | EDP |
| Project owner | EDP |
| Actors who receive benefits | Local community |
| Legal background | . |
| Background information | In 2006, 74% of Portugal's total renewable energy production was from hydropower plants and the Government has announced the intention to award 10 new hydro plants with a total capacity of 1,096 MWs. The following measures are available in Portugal to further stimulate the hydro market: fixed feed-in tariffs per small hydro ( as well as for PV, wave energy, small hydro, wind power, forest biomass, urban waste and biogas), investment subsidies and tax reductions. A participatory approach is being explored in the construction process of the hydro plants of Sabor, Tua and Fridao whose regions have strong similarities: limited offer of medical, social and tourism services, lack of infrastructures; high unemployment, low education rate and an ageing population . |
| Type of benefit sharing mechanism | Benefits in kind |
| Renewable energy source | Hydropower |
| Application of BSM | Benefits in kind: In order to increase the community acceptance to the hydro projects, EDP has conducted studies on community expectations and their risk perception and has set up a well-structured consultative process to facilitate social participation. These procedures have permitted to establish strong local relations and partnerships through strong communication channels. This process demonstrated that the citizens' main expectations from the project focussed mostly on generating opportunies for economic development such as local employment, tourism, road access and the possibility for reduced energy prices. In line with these expectations, the EDP Foundation has started to implement programs such as social support for retired population, educational and cultural programs for young people. |
| Factors which contributed to the success of the project | Elaboration of a 'Community involvement plan' by EDP which included assessment measures and the measurement programs Involvement of the local authorities from the very start of the construction process . Emphasis has been placed on identifying the correct stakeholders and on allowing their involvement during all project phases. |
| Roles of the different stakeholders | EDP is the engine of the process and has covered the additional costs in respect to the compliance with the basic legal compensation measures and is addressing the citizens' expectations through the EDP Foundation. Major efforts have been placed on overcoming the ‘ lack of participation’ culture and local authorities and citizens have responded positively to the consultative procedures and to the EDP Foundation programmes. |
| Difficulties which had to be overcome | Lack of participation culture from Portuguese society: The historical record of hydro-power plants built in the fifties and sixties did take local communities and stakeholders involvement and participation into consideration. Weighing the community expectations in order to avoid possible disappointment and/or the feeling of limited intervention power. The community of Amarante opposes the construction of downstream dam in Fridão as the water level in the Tâmega river would rise in the city. They argue that a higher water level poses an increased threat of floods in the city. They also fear that higher water levels would destroy the banks of the river, affecting the view of the city and removing the ability to enjoy walks along the river and instead replacing it by polluting and noisy entertainment such as jet-skis. |
| Impact of BSM of this project on community acceptance | As it is an ongoing process is too early to evaluate its long term impacts on acceptance of the new hydro plants. |
| Planned production of MW by your project | Sabor: 171 MW, Tua: 251 MW, Fridao: 238 MW, |
| Website | http://www.a-nossa-energia.edp.pt |
PV Soundless |
|
| Name of the project | PV Soundless |
| Country | Germany |
| Description | In 2001 a grid-connected photovoltaic sound barrier was constructed at Freising. At the time of construction this PV sound barrier was the highest yielding sound barrier of the world with a total capacity of 718 kW. |
| Project developer | Utility Freising, Gehrlicher Solar, Consultant M. Grottke |
| Start date | 23-12-2002 |
| Total investment (€) | 3,6 million |
| Financing sources | Shareholder Equity (Utility Freising, Local Private Investors) National public financing for sound barrier European Commission Co-Financing (minor part of PV system) Debt financing |
| Initiator | Utility Freising, Gehrlicher Solar, Isofoton, Consultant M. Grottke |
| Investor(s) | Utility Freising and private investors of the region |
| Project owner | Utility Freising and private investors of the region |
| Actors who receive benefits | Utility Freising and private investors of the region & surrounding residents |
| Background information | Highway traffic increase and a parallel grow of the municipality of Freising required the construction of a noise barrier between the highway and the newly created industrial real estate area of the municipality. At the same time the citizens of Freising are very active in the clean electricity sector. The concept of combining a sound barrier with a PV system seemed an ideal manner to combine two public goods. |
| Type of benefit sharing mechanism | Local ownership/co-ownership Benefits in kind |
| Renewable energy source | Solar energy |
| Application of BSM | Local ownership: in the first two subsystems of the PV installation local citizens were offered the possibility of purchasing shares in the project. Benefits in kind: combining the public good of a sound barrier with the generation of solar energy. |
| Factors which contributed to the success of the project | Political Support: the municipality of Freising is actively involved in promoting renewable energy and has large ambitions in this field. Gathering the required permits for a noise barrier and PV system requires the collaboration of several public actors such as the utility, the organisation in charge of highway maintenance and the municipality. As the municipality was the initiator this greatly speeded the process of realising the project. |
| Roles of the different stakeholders | Local politicians (strong green party) are pushing the municipality of Freising to reach 100% clean electricity generation within medium-term The municipality of Freising is the 100% owner of the utility Freising which installed the system The municipality of Freising via its utility has direct links to other relevant stakeholders, such as the organisation in charge of highway maintenance |
| Impact of BSM of this project on community acceptance | The project demonstrates on a larger scale the possibilities of integrating renewable energy solutions in other public goods such as sound barriers which have a high rate of public acceptance. |
| Impact of BSM of this project on socio-political level or market acceptance | Market Acceptance: in Germany this project is used as an example for other PV noise barriers. The constructer actively promotes this product. |
| Planned production of MW by your project | 718 kW |
Solar Park Rothenburg |
|
| Name of the project | Solar Park Rothenburg |
| Country | Germany |
| Description | A grid-connected 20,6 MW PV system was installed on the former airport area. It is one of the largest solar photovoltaic systems installed in Germany and has a surface of approximately 68 ha (the area required is around 2,9 ha per MW). The expected annual yield should exceed 20 GWh. Project development, project financing and project installation was realised by Gehrlicher Solar AG. |
| Project developer | Gehrlicher Solar AG |
| Start date | 14-04-2009 |
| Total investment (€) | 60 million |
| Financing sources | Private capital of Gehrlicher Solar AG, private capital of the utility Munich (Stadtwerke München GmbH) and co-financing via banks. |
| Initiator | Gehrlicher Solar AG |
| Investor(s) | Gehrlicher Solar AG, private investor, Stadtwerke München GmbH |
| Project owner | Gehrlicher Solar AG, private investor, Stadtwerke München GmbH |
| Actors who receive benefits | The assiciation of communities Rothenburg Görlitz, local Airport |
| Legal background | In Germany the local network operators must pay for grid extension measures. These costs are then forwarded to the clients via network charges. For the investor the installation area must be classified as a 100% conversion area. Otherwise the feed-in tariff might not be paid after the system is operational. |
| Type of benefit sharing mechanism | Benefits in kind Local contracting Local employment Indirect social benefits |
| Renewable energy source | Solar energy |
| Application of BSM | Benefits in kind: the local airport was threatened with closure. As the PV park was built on land of the airpot it makes periodic payments for land use which together with business taxes allow the airport to remain operational. Local Contracting: During the construction phase of the PV park local contractors were employed for the instalment which are now employed for its maintenance. Local employment: the PV park created new jobs for operation and maintenance which are shared with the airport Indirect Social Benefits: as the airport can remain open thanks to the PV park, many existing jobs were preserved. |
| Factors which contributed to the success of the project | Legislative factors played an important role, as the airport was designated a 'conversion' area leading to higher revenues to the local authorities and allowing the local airport to remain open. Political support also played a large role as the head of the district authority was the previous mayor of Rothenburg. He was aware of the financial problems the town was facing and significantly supported the project to secure funds to allow the airport to remain functional. |
| Roles of the different stakeholders | Head of district authority: as previous mayor of Rothenburg he provided a great level of support for the project, and helped work away bottlenecks. |
| Difficulties which had to be overcome | The local network operator was hesitant to make the grid connection with the PV park. The costs for the grid extension would have to be forwarded to its clients, and the higher the share of fluctuating renewables, the higher the charges which have to be asked from its clients. Also the area developed must be designated a 100% 'conversion' area to receive the correct feed-in tariff. The designation is often uncertain however, which creates difficulties for the developers during the planning phase. |
| Impact of BSM of this project on community acceptance | The fact that the construction of the PV park used local contractors, created local jobs and preserved old jobs in the airport helped create a broad level of community acceptance. |
| Planned production of MW by your project | 20 MW |